Convert Old Intake into new SonoSteam Process for Compylobacter

Client: Faccenda Foods

Requirement: Convertion of Intake Shed to Production Area

Value: £1.2million

Programme: 12 Weeks

Installation of two new SonoSteam machines into the pre-chill lines

On 8th March we received approval to start work on a project to install two new SonoSteam machines into the pre-chill lines.

The project involved a complete refurbishment of the old line 1 intake area, and the pre-chill track works being diverted through this room to enable all birds to be processed in SonoSteam machines.

The challenge was to have the works complete for the end of May the same year.

“In order to succeed, we must first believe that we can.”

Quote by Nikos Kazantzakis

Maintenance access included in the platform design, with full structural calculations and CE certification.

Engineered to be fitted over the existing process area within the existing portal frame.