Client: Faccenda Foods
Requirement: Convertion of Intake Shed to Production Area
Value: £1.2million
Programme: 12 Weeks
Installation of two new SonoSteam machines into the pre-chill lines
On 8th March we received approval to start work on a project to install two new SonoSteam machines into the pre-chill lines.
The project involved a complete refurbishment of the old line 1 intake area, and the pre-chill track works being diverted through this room to enable all birds to be processed in SonoSteam machines.
The challenge was to have the works complete for the end of May the same year.
“In order to succeed, we must first believe that we can.”
Quote by Nikos Kazantzakis
Maintenance access included in the platform design, with full structural calculations and CE certification.
Engineered to be fitted over the existing process area within the existing portal frame.